Farnsworth and Forrest Street Drainage Upgrade

  • Project typeRenewal
  • Project scheduleOn schedule
  • Completion Date30 June 2027
View of intersection of Farnsworth and Forest Street intersection

Mount Alexander Shire Council is committed to upgrading, maintaining and rehabilitating local infrastructure in an efficient and timely manner.

Following the significant rainfall and flash‑flooding events of 2022, several areas across the shire were identified as requiring improved stormwater management. One of these priority locations is the Farnsworth Street and Forest Street catchment in Castlemaine.

The existing drainage system in this area includes both piped stormwater infrastructure and an overland flow path that carries water toward View Street and Forest Street. During heavy rainfall, the current underground network becomes overwhelmed, contributing to localised flooding.

This project aims to upgrade the underground stormwater connection along sections of Farnsworth Street, View Street and Forest Street to improve drainage capacity, reduce flooding risk and enhance the resilience of the local road network. Detailed drainage and kerb designs have been completed to guide construction.

Project location

The project is located at the intersection of Farnsworth Street and Forest Street in Castlemaine, extending along parts of:

  • Farnsworth Street
  • View Street
  • Forest Street

This area forms a key stormwater catchment where underground drainage transitions to an overland flow path. Improving this connection will help reduce flooding impacts on nearby roads, properties and public spaces.

The area of work is shown in the image below.

Location map of drainage works on Farnsworth and Forest Street

Design considerations

The drainage upgrade at the intersection of Farnsworth Street and Forest Street has been designed to address the specific hydraulic, environmental and physical constraints of this catchment. Key design considerations include:

  • Stormwater capacity and flow behaviour — the 2022 flash‑flooding events highlighted that the existing underground system cannot convey peak flows. The new design increases pipe capacity and improves flow efficiency to reduce surcharge and overland flooding.
  • Integration with the existing overland flow path — the catchment naturally directs water toward View Street and Forest Street. The design ensures the upgraded underground system works in tandem with this overland path rather than against it.
  • Pipe sizing and alignment —pipes have been selected and sized to meet current and future hydraulic demands, while fitting within the constrained road reserve and avoiding existing services.
  • Drainage pit placement and inlet efficiency — pit locations and grate types have been chosen to maximise capture of surface water, reduce bypass flows and improve safety for road users.
  • Existing service conflicts — the design accounts for water, sewer, gas, electricity and telecommunications assets, adjusting pipe alignments and depths to avoid clashes and maintain safe clearances.
  • Kerb and channel redesign — new kerb profiles and laybacks are designed to improve surface drainage, direct runoff to pits and ensure driveway tie‑ins meet accessibility and safety requirements.
  • Environmental protection and vegetation impacts — tree‑root zones, vegetation removal and reinstatement requirements have been incorporated into the design to minimise environmental disturbance.

These design considerations ensure the upgraded drainage system will perform reliably during major rainfall events, reduce localised flooding and improve the resilience of the surrounding road network.

Where are we now?

The project has progressed through several key stages:

  • Drainage and kerb design is complete, including detailed construction drawings.
  • Site investigations have been undertaken to confirm existing conditions and service locations.
  • Construction documentation—including technical specifications, tender requirements and environmental controls—has been finalised.
  • Contractor engagement will commence shortly, with works to be delivered in accordance with the approved plans and specifications.

Once construction begins, the contractor will establish the site, implement traffic management, notify nearby residents and commence staged excavation and installation works.

Project timeline

The exact dates will depend on contractor scheduling, weather conditions and permit approvals, but the project is expected to be delivered within the next financial year, subject to budget funding.